LIFTING OF A BRIDGE IN PORT-LOUIS
MAURITIUS / MAURITIUS
Lifting of two bridge girders of 37 meters and 66 tons each, above the M2 motorway.
A delicate operation due to the length and weight of the beams.
Our GMK 5220 (220T) crane was pushed to 92% of its capacity!
November 2021
FIRST WALLS
New Caledonia
Lifting and assembly of prefabricated walls (100 tons in total) as part of the construction of a storage dock.
May 2021
DISMANTLING OF MARITIME EQUIPMENT
The meeting
For the coastal road grouping, our Grove 400T mobile crane participated in December 2020 in dismantling the ENERPAC submersible platform present on the viaduct site.
This barge was used for additional ballast at sea.
Our 400t was necessary since the largest mass weighed 38t for a span of 25m.
June 2021
INSTALLATION OF A PEDESTRIAN WALKWAY
Mauritius / Mauritius
The Mauritius teams have installed the pedestrian bridge that connects the Victoria Urban Terminal to the Metro Express platform.
This project, which changes the decor of Port-Louis, required the mobilization of around thirty workers.
To lift this bridge weighing 80 tons in total, we have made available to our client our crane Grove GMK 5220.